A bill is not a law, and the distance in this 1 is exact. Bill 42, the Energy, Environment and Utilities Statutes Amendment Act, 2026, was introduced in the Alberta legislature on November 18, 2026. If passed, it would bar a data centre of 10 MW or more from a site within 600 metres of the nearest home.
Direct answer: The provincial release sets 3 land lines and 1 money line. No large data centre within 600 metres of a home. No large data centre on the province’s highest quality farmland or on irrigated land. A water standard aimed at cooling use close to zero. And a designation that makes the proponent pay for its own power infrastructure, with no pass through to Alberta ratepayers.
Which land does the bill protect?
The farmland line covers about 14 million acres of Class 1 and Class 2 land. It also covers Class 3 land in municipalities that hold no Class 1 or Class 2 land. Irrigated land is protected in its own right.
The setback carries 1 exception route. In certain circumstances, a municipality may set an alternative setback where local planning supports compatible development. The province draws the floor. The town may argue about the distance above it.
Existing noise rules continue to apply. The release also raises the maximum fine for serious environmental contamination to $6 million for a corporation, on top of cleanup duties that already exist.
Who pays for the power?
The bill creates a Data Centre Designation. Under it, a proponent covers the cost of its own power infrastructure project. The cost cannot pass to Alberta ratepayers.
The designation builds on an existing rule. A data centre must already show that it puts no strain on grid reliability, and it must cut its own use first in an emergency, before households or essential services are asked to cut. The bill adds a design point beside the money point. A data centre should be built so its excess heat can be recovered for greenhouses, industry or homes.
The sequence in Alberta now runs on 2 clocks. Calgary votes on a data centre freeze on November 17. The application clock runs the same day covered the city file, where council directed its own bylaw drafting with a public hearing expected in March 2027. The province moved 1 day later with the wider instrument. A project near a city boundary can sit under both files at once, and the stricter reading governs the schedule.
The pattern matches the record in Data centres lose at the polls. Consent is the new permit. Consent work that used to sit with the proponent now sits in statute. The full provincial picture sits in Canada Data Centre Map: What Is Built, Blocked and Waiting, and Bill 42 moves Alberta’s rows from announced to proposed law.
Recap: Bill 42 is tabled, not passed. Its lines are 600 metres from a home, 10 MW as the threshold, top farmland and irrigated land closed, cooling water aimed close to zero, and power infrastructure paid by the proponent. The regulations under it are still unwritten.
Watch the bill’s stage, not the speeches around it. The next hard date in this file is the March 2027 Calgary hearing, and any project that cannot state its distance, its land class and its water plan before that date is not ready to file.