Peace Bridge and downtown Calgary skyline in winter, the city weighing a data centre moratorium

Calgary’s data centre pause hangs on one undefined word

Calgary’s motion pauses rezoning for large data centres until March 2027 but never defines large. Alberta landowners and builders should check exposure.

The Calgary data centre moratorium turns on one word. Notice of motion EC2026-01010, filed October 28, 2026, would stop new rezoning applications for “large-scale” data centres from reaching council until March 2027. The motion never defines large-scale. Read clause by clause, that gap decides which Calgary businesses are caught.

Key points

  • Instrument: notice of motion, report EC2026-01010, item 5.2.2, for Executive Committee on November 3, 2026. Proposed, and no bylaw is in force.
  • Scope: new land use redesignation applications for large-scale data centres. Land already zoned for the use is a separate question.
  • Draft bylaw amendments defining data centres by scale are due at the March 2027 public hearing; water and infrastructure reports follow no later than Q4 2027.
  • Five municipalities named in the motion already have temporary restrictions.

What the Calgary data centre moratorium directs

The operative clause directs the chief administrative officer to stop bringing new land use redesignation applications for large-scale data centres to council for decision. The pause runs until a report and possible amendments to Land Use Bylaw 1P2007 come back, targeted for the March 2027 public hearing. By its own terms it bans nothing and leaves small and medium sites alone.

Advertisement

The notice of motion is sponsored by Councillors Wyness, Dhaliwal, Yule and Pantazopoulos and Mayor Farkas. Three further pieces of work sit in the same clauses: reaffirming water servicing terms with regional partners, a report on risks and possible tax and bylaw changes, and a report on cumulative water security. The last two are due no later than Q4 2027.

The detail that matters most is an absence. Bylaw 1P2007 has no definition of a data centre at all, so every proposal is now judged against general rules. That is the problem the motion is really trying to fix.

The undefined word, and who it reaches

The motion’s preamble says small and medium-scale data centres have needs comparable to other commercial and industrial businesses and belong to the city’s ordinary business base. A Calgary firm renting rack space, running a server room or buying cloud capacity is plainly outside the target. Developers rezoning land for very large campuses are plainly inside it.

Between those poles the text is silent. Megawatts, floor area or water draw could each set the line, and each would catch a different set of projects. Until the March 2027 report proposes a definition, a mid-sized edge facility or a local AI hosting company cannot know which side it sits on.

Regional customers carry a quieter exposure. Calgary supplies water to neighbouring municipalities, and the existing servicing agreement already requires them to notify the city when a new large customer exceeds one megalitre a day of potable water or wastewater flow. The motion asks the city to reaffirm those terms, which puts water-cooled projects just outside city limits on notice as well.

Where Calgary sits among Canadian municipalities

Calgary is following. The motion’s preamble lists five municipalities with temporary planning restrictions, one that paused zoning changes and three rewriting their bylaws, across six provinces. For a site selector, local land use rules now belong in data centre risk planning well beyond Alberta.

Restricted applications
Rocky View County, AB
Oakville, ON
Cumberland, NS
Saskatoon, SK
Mississauga, ON
Paused zoning changes
Miramichi, NB
Reviewing bylaws
Essex County, ON
Terrace, BC
Mountain View, AB
Proposed
Calgary, AB (Executive Committee, November 3, 2026)

Source: City of Calgary notice of motion EC2026-01010, as listed in its preamble. Text summary: five municipalities restrict applications, one paused zoning changes, three are reviewing bylaws, and Calgary’s motion is proposed.

High-voltage transmission towers on a dry prairie field, the power question behind the Calgary data centre moratorium

Our reading: support the pause, set an interim number

Defining a use before approving more of it is ordinary planning practice, and a bylaw with no data centre definition invites case-by-case fights. A pause tied to an undefined term, though, shifts uncertainty onto every mid-sized project. Council should ask for an interim threshold on November 3, even a rough one.

The reason is capital. Alberta’s push for AI infrastructure, covered in our look at data centre projects in Olds and Bonnyville, means investment will move to whichever municipality offers clear rules first. An interim line keeps the small operators the motion praises out of a queue meant for campuses. Councils elsewhere in Alberta face a money question as well, since the Alberta data centre levy goes to the province and the servers stay off the municipal tax roll.

The opposing view is reasonable: any number set now would be arbitrary and quickly gamed, and a short, clean pause beats a hurried definition. We still hold our reading. The preamble already distinguishes scales in words, so turning that into a provisional figure is a smaller step than it looks.

Before November 3: four checks

Plan as if a rezoning answer arrives no earlier than March 2027. Firms that only buy hosting or colocation need little beyond a question to their provider. Developers with live applications should confirm with the city whether theirs counts as large-scale.

  1. List every Calgary or regional site in your plans that would need a land use redesignation.
  2. Write down its expected power draw and daily water use, so you are ready when a threshold is proposed.
  3. If the site is in a regional municipality on Calgary water, check it against the one megalitre a day notification trigger.
  4. If you rent capacity, ask your provider whether its next Calgary expansion depends on rezoning.

National principles, covered in Canada’s data centre power principles, will not settle a Calgary zoning question. The municipal layer now matters on its own, as the AI data centres in Canada hub tracks. Nova Scotia chose a different lever: its AI campus at Point Tupper buys grid power only on an interruptible basis, and we ran the per-megawatt and per-job math on that Nova Scotia data centre.

FAQ

Has Calgary banned data centres?

No. The motion proposes a temporary moratorium on bringing new rezoning applications for large-scale data centres to council. It is a notice of motion going to Executive Committee on November 3, 2026, and is not in force.

Does the Calgary data centre moratorium affect small data centres?

The motion suggests it does not. It says small and medium-scale data centres have needs comparable to other commercial businesses, but it does not set a size threshold. The motion text leaves that to the March 2027 report.

When will Calgary define data centres in its land use bylaw?

The motion asks for proposed amendments to Land Use Bylaw 1P2007 at the March 2027 public hearing, with reports on infrastructure and water security no later than Q4 2027.

The next date is November 3, 2026, when Executive Committee reviews the motion. Before then, any business with a Calgary site that needs rezoning should have its power and water figures written down.

Last fact-checked October 29, 2026 against the City of Calgary notice of motion. General information only, and no substitute for legal or planning advice.

Total
0
Shares
Prev
Skip the loss line. Anthropic’s S-1 warns buyers their Claude terms will change
Printed business report with charts, like the Anthropic S-1 risk factors and financial tables

Skip the loss line. Anthropic’s S-1 warns buyers their Claude terms will change

The Anthropic S-1 risk factors say pricing, rate limits and models may change

Next
Before you blame AI for fewer junior hires, read StatCan’s new numbers
Young job candidate shaking hands after an interview, a moment that is rarer as youth hiring in Canada slows

Before you blame AI for fewer junior hires, read StatCan’s new numbers

StatCan data shows youth hiring in Canada fell most in jobs with little AI

You May Also Like